No. Deliverable Title Lead beneficiary  Due Date
D1.1 Project management and quality control plan 1 – ENoLL May 2021
D1.2 First version of Ethics and Safety Manual 2 – AUTH September 2021
D1.3 Final version of Ethics and Safety Manual 2 – AUTH March 2023
D1.4 Data management plan (first version) 12 – UPM September 2021
D1.5 Data management plan (final version) 2 – AUTH September 2023
D2.1 Standard Version 1 1 – ENoLL September 2021
D2.2 Evaluation process and tools 16 – LLSA March 2022
D2.3 Standard Version 2 1 – ENoLL March 2022
D2.4 Standard Version 3 1 – ENoLL September 2022
D2.5 Standard Version 4 1 – ENoLL March  2023
D2.6 Standard Version 5 1 – ENoLL September 2023
D2.7 Standard Version 6 1 – ENoLL March 2024
D2.8 First version of user requirements 2 – AUTH January 2022
D2.9 Final version of user requirements 2 – AUTH March  2023
D3.1 VITALISE Service specification 8 – VICOM September 2022
D3.3 Anonymisation and Synthetic data algorithm 8 – VICOM July 2023
D3.4 Panel Management Tool 2 – AUTH July 2022
D3.5 VITALISE SDK Manual 8 – VICOM September 2022
D3.6 Certified Node OS installation image 13 – WITA July 2022
D4.1 Online educational material (first version) 1 – ENoLL September 2022
D4.2 Online educational material (final version) 1 – ENoLL March 2024
D4.3 Printed educational material (first version) 1 – ENoLL September 2022
D4.4 Printed educational material (final version) 1 – ENoLL March 2024
D4.5 Living Lab Guidelines (first version) 1 – ENoLL March  2023
D4.6 Living Lab Guidelines (final version) 1 – ENoLL March 2024
D4.7 University Course design 2 – AUTH September 2022
D4.8 Boosting commercialisation potential of research results 14 – AV March 2022
D5.2 Ethical application documents for JRA1 4 – LICALAB March 2022
D5.3 Summary and results of the performed activities for JRA1 7 – GAIA March 2024
D6.2 Ethical application documents for JRA2 2 – AUTH March 2022
D6.3 Summary of the performed activities for JRA2 12 – UPM March 2024
D7.2 Ethical application documents for JRA3 3 – LAUREA March 2022
D7.3 Summary of the performed activities for JRA3 5 – INTRAS March 2024
D8.1 First interim report on Transnational Access 1 7 – GAIA July 2023
D8.2 Final report on Transnational Access 1 7 – GAIA March 2024
D9.1 First interim report on Transnational Access 2 2 – AUTH July 2023
D9.2 Final report on Transnational Access 2 2 – AUTH March 2024
D10.1 First interim report on Transnational Access 3 5 – INTRAS July 2023
D10.2 Final report on Transnational Access 3 5 – INTRAS March 2024
D11.1 Material for open calls 11 – SIT September 2023
D11.2 Application toolkit 11 – SIT September 2023
D11.3 Evaluation procedure and accepted proposals 11 – SIT November 2023
D12.1 Final interim report on Virtual Access 12 – UPM March 2024
D12.2 Report from VITALISE platform access and usage 12 – UPM March 2024
D13.1 Dissemination and Communication plan 15 – VILABS June 2021
D13.2 Dissemination and Communication activities report (first version) 15 – VILABS September 2022
D13.5 Dissemination and Communication activities report (final version) 15 – VILABS March 2024